ADVANCE THE RENOVATION OF THE STATIONS IN THE NORTH BELGRANO TRAIN

The works to renovate the 22 stations of the line joining Pilar Buenos
Aires are underway. Among the improvements include elevated platforms,
building ramps for the disabled, new shelters, seats and LED lighting. This
work will benefit 108,000 passengers using the train Belgrano Norte every
day.
Friday August 2, 2019
Argentinos railway infrastructure under the Ministry of Transport of the
Nation agency, advances in the renewal of the Belgrano Norte train
stations, linking the Villa Rosa station in Pilar, with his head in Retiro.
These works involving an investment of US $ 88 million is the first step to
modernize the line.
"We are doing the works they were delayed for long and will have a very
favorable impact on quality of service. Passengers begin to see this year
the result of the works that guarantee equal access to all people. In
addition, we are installing the automatic braking system, a vital railway
safety in that never before had done investment, "said Guillermo Fiad,
president of Argentine Railway Infrastructure.
The works will improve accessibility and travel experience of the 108,000
passengers who use this line every day. They are rising to the platforms
are at the same height of the train is standing guide tiles and building
ramps for the disabled; new shelters, restrooms, seats, ischiatic supports
and pinwheels SUBE in revenues and expenditures of each station will be
installed.
The works are being carried out sequentially prioritizing both headers,
Retiro and Villa Rosa, as well as Ciudad Universitaria, Aristobulo del
Valle, Carapachay, Boulogne and Don Torcuato. This criterion was determined
phasing in order to focus efforts on enable stations having greater flow of
passengers or particular demands then advance elsewhere.
Because of a court ruling in 2007 in response to a motion filed by the
Ombudsman's Office, the Justice forced the concessionaire Ferrovías and the
National State to each of the stations count on fixed ramps and
mobile-station within 90 days. These works had not been faced so far and
are now running.
As work progresses, the train service will continue to operate normally in
makeshift platforms that are inspected weekly by train staff Argentinos
infrastructure, contractors and Ferrovías, to keep them fit for service
operation.
Also it is moving forward with the installation of automatic braking in all
trace of the Belgrano Norte line, in which we are investing U $ S5,3
million. The system will be operational later this year along the 106
kilometers long, in addition to the equipment in 25 locomotives and 5 cars.
In the Roca train it is already in operation, while the work plan provides
for the incorporation of the system to other lines.
These works are part of the modernization North Belgrano train. As part of
this process, the state is auctioning the concession line. In this new
contract is contemplated investment in new trains with automatic gates and
improvement works for the line.
The Ministry of Transport of the Nation launched a Comprehensive Plan of
Railway Works by US $ 14 billion to transform the way of train travel
throughout the metropolitan area.

Most Read:

[English-Español] CAPACITACIÓN ONLINE EN PREVENCIÓN DE LA VIOLENCIA CONTRA ADULTOS MAYORES

[Français-Español] FINALIZACIÓN DE LA ROTACIÓN

[Deutsch-Español] A 71 AÑOS DE SU CREACIÓN, WADO DE PEDRO VISITÓ LA DIRECCIÓN NACIONAL DE MIGRACIONES

[Français-Español] AVANZAN EN UN PROYECTO DE LEY PARA ABORDAR LA VIOLENCIA EN EL DEPORTE

[English-Español] ARCHIVO GENERAL FERROVIARIO

 URBAN INFRASTRUCTURE WORKS WERE INAUGURATED IN ROQUE PEREZ

[Deutsch-Español] ARGENTINA REFUERZA LA COOPERACIÓN CON FRANCIA EN SEGURIDAD AÉREA