NATION ADVANCES IN THE RECOVERY OF THE RN 98 IN NORTHERN SANTA FE

Patching works and repaving are held over 123 kilometers of the road,
between Vera and Tostado, through an investment of $ 890 million by the
Ministry of Transport of the Nation, through National Roads Authority. And
they completed 28 km and advanced to the recovery of the road another 50 km
more.
Wednesday May 29, 2019
The first 28 km were executed repaved from Vera west and included patching,
milling and reconstruction of the road in the most damaged points. On these
arrangements a new layer of pavement was placed and was completed with the
horizontal demarcation.
Currently, progress is paving another 5 kilometers on the most damaged
sectors and tasks patching, milling and recycling ridges on another 35
kilometers are made. In this intermediate section, between 28 and 58
kilometers corridor, from July final pavement layer is placed in to
complete the full recovery of the walkway in that area.
"The presence of the National State in northern Santa Fe was essential to
recover the RN 98 that was abandoned and impassable and today shows its
progress. Despite being the only road link between east and west Santa Fe,
it was shunned by many users because of their poor condition. Now you can
choose again this way, saving time and travel costs to mobilize this
growing region that is of vital importance for the movement of agricultural
loads. The work started just over a year, and 65% completed despite the
affectations of the water emergency area suffered repeated by the
rains, "said Patricia Gutiérrez, General Administrator of the National
Highway.
Facing the water emergency in the region, both by heavy rains in place as
the mass of water moving from the south chaqueño from National Roads
Authority works were carried out along 100 kilometers of the stretch of
work involved. They consisted of cleaning and shaping of the zone parallel
to the road way, favoring the water draining and avoiding waterlogging and
in neighboring fields in the route itself.
Also, due to the flooding of the Golondrina stream product flooding
protection works bridge abutments that crosses over the RN 98 were
conducted stone bulk and gabions was placed and strengthening the body's
Causeway was conducted alteo on a stretch of about 300 meters.

Most Read:

HE STARTED THE SECOND NATIONAL ENVIRONMENTAL ASSESSMENT

[Italiano-Español] MINISTERIO DE DESARROLLO TERRITORIAL Y HÁBITATFERRARESI RECIBIÓ AL LEGISLADOR PORTEÑO JUAN MANUE...

[Italiano-Español] MINISTERIO DE DESARROLLO SOCIALAVANZAN LAS OBRAS DE URBANIZACIÓN DE BARRIOS POPULARES EN TODO EL...

NARCOMENUDEO: INCREASE MORE THAN 400% THE DRUG SEIZURE

THE SSN ADVANCES IN THE MANAGEMENT MODERNIZATION PLAN

ATTENDING ENABLES DEVELOPERS SAN JUAN AND BUENOS AIRES